Wind Turbine DFIG Slip Ring Fault: Case Study
Over 60% of all wind turbines are currently using the doubly fed induction generators (DFIGs). At the time of their introduction they offered higher efficiency (in sync with grid with variable wind turbine speed). And also better power factor control (import/export of reactive power).
In addition, reduced converter cost (only 25-30% of power passes through the convertor) compared to the previous generation of generators. This is possible by connecting the rotor windings to the grid via a multi-phase slip ring unit and a voltage converter. The slip ring unit consists of a set of spring-loaded brushes. They ride on slip rings mounted on the rotor, for each phase.
A number of generator faults are detectable by accelerometers in the load zone of the generator bearings, including faults with the slip ring assembly. This case study shows how early detection of slip ring defects could result in a fast, inexpensive repair. If, on the other hand the slip ring fault is not corrected at an early stage of development, this could lead to a catastrophic failure where the generator is destroyed.
MACHINE/INDUSTRY/PROCESS
A multi-MW wind turbine in a wind park was operating at full production. At that time, Brüel & Kjær Vibro condition monitoring system temporarily disconnected for approximately two months. Shortly after, when the condition monitoring system went back online, the customer notified the Brüel & Kjær Vibro Surveillance and Diagnostics Service Centre. And, requested the initial data analysis.
OBSERVATION/DIAGNOSIS
Then, Brüel & Kjær Diagnostics Group analysed the data using a detailed time waveform and frequency spectrum, as shown in Figures 1-2. Increased vibration indicated a potential problem with generator slip ring unit.
OBSERVATION/DIAGNOSIS (Cont.)
They issued an alarm report by phone conversation with the customer explaining the problem, in the following step. And, below is an extract from the recommendation section of the report:
• In addition, generator inspection within 1-2 weeks is a recommendation.
• Another recommendation is to perform an up-tower generator test run with particular focus on the slip ring unit. Check the height of the slip ring brushes to be within the acceptable limits. Then, inspect the condition of the cooling groves, insulation ring and the current clamps.
RESULTS/FEEDBACK
A site inspection was done one day after the report was issued.
RESULTS/FEEDBACK (Cont.)
Aftermath, the slip ring unit and brushes were replaced. In this way, the wind turbine returned to production with lower vibrations measured on the generator bearings.
BENEFITS/COST SAVINGS ESTIMATION
There are clear benefits in detecting a slip ring fault early. The cost and downtime in replacing the slip ring unit is small in relation to the maintenance and downtime with a catastrophic failure of the generator.
• Slip ring unit replacement: Approximately, 4000 € plus a few hours downtime (500-1000 €) • Generator replacement: With approximation, 100 000 € (includes crane) plus downtime (four weeks at 2000 € per day), with a total of 156 000 €
Hence, this gives a savings of 151 000 €, which does not include labor.
-
Events5 years ago
Canada and Turkey women working in the renewable energy sector in met
-
Manufacturers of wind turbines5 years ago
GE’s Haliade-X 12 MW prototype to be installed in Rotterdam
-
Operations and Maintenance6 years ago
GENBA is on the rise; another milestone passed by in global existence
-
Genel8 years ago
EWT launches the DW61, It’s most efficient and high energy producing wind turbine
-
Genel9 years ago
Internet of things will empower the wind energy power plants
-
Turbine Manufacturing6 years ago
İğrek Makina focused on developing and producing Machine Tools and Wind Energy Turbines
-
Energy management systems5 years ago
Demand/Supply – Renewable energy with guarantees of origin (GO)
-
Events5 years ago
Key Players from 10 Nations will Show Their Strong Positions at APWEE
-
Manufacturers of wind turbines4 years ago
ENERCON installs E-160 EP5 prototype
-
Manufacturers of wind turbines5 years ago
The Nordex Group receives first order for Delta4000 turbines from the USA
-
Genel8 years ago
Zorlu energy envisages a bold new future based on renewables
-
Manufacturers of wind turbines5 years ago
ENERCON and Lagerwey together develop two new WEC types